On November 5, the second of eight RES auctions scheduled for this year took place. It was an auction for new installations with an installed electrical capacity of more than 1 MW, using only non-agricultural biogas (landfill, biogas from sewage treatment plants), dedicated biomass combustion installations, hybrid systems, including high-efficiency cogeneration, as well as thermal waste treatment installations. and dedicated multi-fuel combustion installations.
In this basket, the amount of energy that can be sold was almost 11 TWh, and its value almost reached PLN 5.2 billion. Three bids were submitted in the auction. Two of them won – those that were submitted by thermal energy companies. Nearly 0.32 TWh of energy worth approximately PLN 123 million was contracted. The minimum price at which the energy was sold was PLN 379.95 / MWh, while the maximum – PLN 407.76 / MWh. The volume of energy contracted as a result of the auction will receive support in the years 2023–2038.