Polskie Sieci Elektroenergetyczne already have contracts and connection conditions with investors of offshore wind farms for a total capacity of approx. 8 GW.
“We will be ready to take power from the sea to the shore. The Energy Regulatory Office adopted on June 1 the network development plan, which provides for investments worth PLN 14 billion.” The network development plan has been approved by the Energy Regulatory Office so that power networks can give energy security, “says Tomasz Jakubowski, operational director of PSE.
“Connection agreements with a total capacity of 2-3 GW have already been signed, and the issued connection conditions relate to a total capacity of 5-6 GW.” So we have about 8 GW of offshore capacity “- emphasizes Tomasz Jakubowski